City of Wichita - 2006 Pawnee, from Broadway to Palisade, Widened
Saturday, May 17, 2008 :: Currently 57 degrees in Wichita

Woman reading newspaper

Community Relations
City Hall, 13th floor
455 North Main
Wichita, KS 67202

Hours:
8 AM-5 PM
Monday-Friday

Phone: (316) 268-4351
Fax: (316) 268-4519

Dale Goter
Government Relations Director

Van Williams
Public Information Officer

Lauragail Locke
Marketing Services Director


View archived news releases by year:

Leaving City Of Wichita Website


Pawnee, from Broadway to Palisade, Widened

Date: October 17, 2006
Contact: Gail Williams, Assistant to the Director of Public Works
E-mail: GWilliams@wichita.gov
Phone: (316) 268-4497

 

Pawnee, from Broadway to Palisade, will be widened from four to five lanes beginning today, Oct. 17. The $1.6 Million project, which will include medians and left turn lanes, is expected to be complete in March 2007. Due to traffic flow on a major street, the contractor will work a six-day workweek. Contractors begin working around 6:30 AM and stop around 6:00 PM.

Construction will be performed in four phases to lessen the impact on neighborhood traffic flow:

Phase 1a: The existing medians from Main Street to just west of Broadway will be removed and temporary asphalt pavement will be installed. Access will be provided to the park entrance and the police station, with drive entrances constructed one-half at a time. One lane of traffic in each direction will be available on Pawnee. Left turns will be permitted.

Phase 1b: Storm sewer will be constructed in the south two lanes of Pawnee. New concrete pavement, curb, gutter and sidewalks will be installed, as well as the south half of the new medians. The south two lanes of Pawnee will be closed. One lane of traffic in each direction will be placed on the north lanes of Pawnee. Left turns will be permitted. Access will be provided to the park entrance and the police station.

Phase 2: Pavement reconstruction of the north two lanes of Pawnee will occur. Storm sewers will be constructed at the intersections of Market, Main and Water. Sidewalks will be constructed on portions of the north side of Pawnee. The north two will be closed, and one lane of traffic in each direction will be placed on the south two lanes of Pawnee. Left turns will be permitted.

Phase 3: Installation of pavement markings and landscaping. Grass areas disturbed by construction will be restored with same seed/sod and existing irrigation systems.

Pavers, Inc., a Salina-based firm, is the contractor.