City of Wichita - 2006 15th Street Lift Station Construction
Saturday, May 17, 2008 :: Currently 57 degrees in Wichita

Woman reading newspaper

Community Relations
City Hall, 13th floor
455 North Main
Wichita, KS 67202

Hours:
8 AM-5 PM
Monday-Friday

Phone: (316) 268-4351
Fax: (316) 268-4519

Dale Goter
Government Relations Director

Van Williams
Public Information Officer

Lauragail Locke
Marketing Services Director


View archived news releases by year:

Leaving City Of Wichita Website


15th Street Lift Station Construction

Date: March 30, 2006
Contact: Gail Williams, Assistant to Director of Public Works
E-mail: GWilliams@wichita.gov
Phone: (316) 268-4497

The City of Wichita has contracted with Wildcat Construction Co., Inc. to construct a sewer lift station and generator building on 15th Street between Ferrell and Jeanette. The project is slated to begin      April 10, 2006 and be completed by July 7, 2006. Construction will be performed in two major phases.

During Phase I, from April 10 to approximately May 8, a new lift station and generator building will be constructed on vacated 15th Street between Jeanette and Ferrell.  During this phase, Ferrell will be closed to through traffic during working hours.

In Phase II, a new sewer line will be bored under the river.  The existing siphon line, located in the middle of Ferrell Street, will be abandoned and the pavement replaced.  Beginning about May 8, the intersection of Ferrell and 15th Street will be closed completely for about 4 weeks.  In the final 3 weeks of the project, inlets will be replaced on Jeanette Street and the generator building completed.