Cost Estimates* |
| Total Land (s.f.) |
$254,750 |
Acquisition cost |
$5.00 s.f. |
$1,273,750 |
| Sitework/Clearance |
Estimated s.f. Demolition cost Site preparation cost Total sitework/site preparation cost |
$2.70 s.f. $2.00 s.f. |
75,000 $202,500 $509,500 $712,000 |
| New S.F. Homes |
16 units |
Ave. s.f./unit Cost/unit (low estimate) Cost/unit (high estimate) Total cost (low) Total cost (high) |
$50.00 s.f. $70.00 s.f. |
1600 $80,000 $112,000 $1,280,000 $1,792,000 |
| New Townhouses |
17 units |
Ave. s.f./unit Cost/unit (low estimate) Cost/unit (high estimate) Total cost (low) Total cost (high) |
$50.00 s.f. $70.00 s.f. |
1200 $60,000 $84,000 $1,020,000 $1,428,000 |
| New Apartments |
80 units |
Ave. s.f. unit Cost/unit (low estimate) Cost/unit (high estimate) Total cost (low) Total cost (high) |
$55.00 s.f. $65.00 s.f. |
950 $52,250 $61,750 $4,180,000 $4,940,000 |
| Total Costs |
Acquisition Sitework/Site preparation Hard construction costs Soft construction costs
Grand Total |
25% |
$1,273,750 $712,000 $8,160,000 $2,040,000
$12,185,750 |
*Assumes new construction in blocks roughly bounded by Topeka, Elm, the alley east of St. Francis, and Pine. Used only as an example of potential costs.
|
 |
|
|